How to Review MRP Reschedule-Out Messages for Open Purchase Orders
The production build moved three weeks. Two purchase orders are still due Friday. Before telling the supplier to hold everything, check whether another order needs some of the material first.
Use MRP reschedule-out messages as a starting list. Compare each firm PO with current allocations, projected stock and the next shortage date. Check supplier terms before proposing a push-out or split.
One material, two PO lines, two decisions
There are 40 usable units and 30 allocated to Tuesday’s work. The next confirmed demand after that needs 150 units three weeks later.
| PO line | Due | Open units | Suggested review |
|---|---|---|---|
| PO-910 / 1 | Friday | 60 | Review for push-out |
| PO-914 / 1 | Friday | 100 | Review for push-out or split |
| Projected balance after Tuesday | Before later build | 10 | Later demand still needs 140 units |
If no other demand or safety-stock rule intervenes, 140 of the 160 ordered units are needed for the later build. You might retain those units with revised dates and review the remaining 20 under the supplier agreement.
Build a time-phased view
Bring in firm PO lines, current usable stock, MRP action messages, and demand with need dates and allocations. Calculate projected balances in date order and keep the site, unit and safety-stock assumptions visible.
Check before sending a supplier request
Review change windows, minimum deliveries, open commitments, and transport lead time. Separate quantities that can move from supply covering an earlier order. Mark an unconfirmed supplier date as unconfirmed.
Make the buyer’s supplier list from the revised plan
Use the action messages alongside the current demand snapshot. Include one row per PO line and any available pegging to demands.
Which Friday PO quantities can move later without causing a shortage or breaking safety stock? Show earliest need date, open units, assumptions and source rows.
Confirm any proposed date with planning and the supplier before updating a firm PO.
Dynamics 365 MRP action messages
The figures and identifiers in this example are synthetic. The displayed arithmetic was checked independently. A live Jolene.pro result could not be verified.
Try this with your own spreadsheet at Jolene.pro. Follow Jolene.pro on LinkedIn for more spreadsheet guides.
For more checked examples, see Jolene.pro Workbook Studies.