How to Check Current Closeout Document Revisions in Excel
A closeout register can show an operations manual as accepted even though the acceptance belongs to a superseded revision. Compare each required document with its current revision and the dated response log as of your handover cutoff.
Line up requirements and responses
In Required, keep Document ID, description and current revision. In Docs, keep Document ID, revision, event date, event type and evidence reference. Use the project’s own status vocabulary. Check duplicate and contradictory responses before refreshing the register.
Reconcile the November 26 cutoff
| Required row | Document | Current revision | Result at cutoff |
|---|---|---|---|
| 2 | M1 operations manual | 2 | Pending acceptance |
| 3 | W1 warranty | 1 | Accepted |
| 4 | A1 as-built | 1 | Missing |
| Docs row | Document | Revision | Date | Event |
|---|---|---|---|---|
| 2 | M1 | 1 | November 23 | Accepted |
| 3 | M1 | 2 | November 25 | Submitted |
| 4 | W1 | 1 | November 26 | Accepted |
| 5 | M1 | 2 | November 27 | Accepted |
These synthetic records show two of three current revisions present and one accepted. Docs!A2:E2 belongs to the old manual and Docs!A5:E5 falls after the cutoff. The warranty is accepted by the cutoff. The as-built has no matching current revision record.
Check the latest valid decision
Filter Docs to the exact document ID and revision and dates at or before cutoff. Sort events by timestamp and check the latest review decision. Show missing, pending, accepted and returned items separately. If equally recent decisions disagree, leave that item for the reviewer. Preserve the evidence reference next to each status, so someone can open the exact submission and response.
See Procore’s guidance on organizing and reviewing submittals. Match the method to the project’s own records and acceptance rules. The example was checked independently.