DatasetsExcel Guides

How to Check Split Receipts Without Overstating Supplier OTIF in Excel

Six units arrived early. The release was for ten.

A first-receipt date can make a partial delivery look on time. To check on-time-in-full delivery, keep the release as the counting unit and add its accepted quantities by the deadline. Later completion does not change what was accepted on the due day.

Start with the supplier-performance question

In a public Epicor practitioner discussion, a buyer asks how others track supplier performance. Replies describe problems caused by changing due dates and stress the need to choose the date basis deliberately.

Microsoft’s supplier-performance documentation distinguishes on-time, in-full and OTIF measures using order-line receipts and a defined reporting scope. This workbook uses a stated release-level policy. It does not reproduce native Epicor or Dynamics scoring.

Three releases, five event rows

All records are synthetic. One company orders one item from one supplier under a single purchase-order line, split into three releases of ten each. Every release has the fixed due day November 18, 2026, in UTC. The complete extract runs through November 24 at 00:00 UTC, with no opening receipts, returns, reversals or unit conversions.

Only posted Accepted quantities count. Draft and Cancelled records do not. There is no grace period or quantity tolerance. A November 18 acceptance must occur before November 19 at 00:00 UTC. The full ordered quantity must be accepted by that deadline for the release to pass.

Release Ordered First receipt by due day? Accepted by due Accepted at cutoff OTIF
R-01 10 Yes 6 10 Fail
R-02 10 Yes 10 10 Pass
R-03 10 No 0 0 Fail

Two of three releases have a first accepted receipt by the due day, or 66.7%. Only one of three passes the full-quantity test, or 33.3% OTIF under this example’s rule. The first-receipt figure is a separate diagnostic. It is not a substitute for full-release performance.

Trace the split before classifying the release

R-01 has six accepted units on November 17 at 09:00 and four on November 20 at 09:00. The two receipts eventually complete the ten-unit release. Only six were accepted by November 18. Its early first receipt does not make it an OTIF pass.

The source events are Receipts!A10:E11. Release identity, ordered quantity and due day are Releases!A10:C10. The reporting cutoff is Releases!C4.

R-02 has five units accepted on November 17 and five at November 18, 23:59:59. Both count. Moving the second acceptance to November 19, 00:00:00 excludes those five from the due-day quantity. The original events are Receipts!A12:E13; the last timestamp is Receipts!D13.

R-03 has a ten-unit Draft record in Receipts!A14:E14. It has no accepted receipt in the complete extract, so accepted quantity is zero. That conclusion relies on the explicit completeness and no-opening-receipts assumptions. An incomplete export would require review.

Keep unresolved releases in view

The denominator is three releases whose due day has ended, not five event rows. Missing accepted dates or quantities, duplicate event IDs and unmapped releases prevent a final complete-cohort rate. The workbook keeps those exceptions visible and withholds the rate instead of dropping the affected releases or treating their uncertain quantities as valid zeros.

For real exports with returns, reversals, mixed units or revised commitments, establish those rules first. This example deliberately keeps one fixed deadline and one normalized unit.

Validation and Jolene test

The workbook passed 840 independent comparisons across 30 test states, including split quantities, duplicate IDs, missing fields, Draft acceptance, cancellation, reordered rows and exact midnight boundaries. Both sheets were rendered and reviewed. All 35 original input cells and key saved results were checked. Native desktop Excel recalculation was not tested.

On November 24, 2026, Jolene read the public XLSX, returned the matching size and SHA-256, and independently reproduced each release outcome, the 33.3% OTIF rate and the separate 66.7% first-receipt diagnostic. Its original input-cell references were checked against the workbook. The native source was also tested after ingestion reported ready with two tables. Its database was readable, but the original workbook, report cutoff and exact-cell metadata were unavailable, so native exact-cell verification remains incomplete.

Download the synthetic workbook

Download the split-receipt OTIF workbook.

The formulas cover three release rows and five event rows. Extend all bounded ranges together when adding data.

Leave a comment