How to Find Double-Booked Technicians When the Team Has Spare Hours
A field-service team has 11 hours of availability and 10 hours of confirmed bookings. The daily total suggests an hour to spare. It still sends one technician to two sites at 10:30 a.m. To find the conflict, check bookings against each technician’s actual work windows.
Check availability in the scheduling system first
In a Smartsheet discussion about part-time staff, a user described weekly allocation being calculated against full-time hours. In Odoo Planning, check employee Working Hours and the Resource view. Odoo says Auto Plan considers working hours, time off and overlapping shifts. An export check is useful when bookings arrive from several systems or the report only shows totals.
Make a one-day check in Excel
This synthetic schedule is for October 28, 2026. Paste the two blocks into sheets named Availability and Assignments, starting at A1. Split columns at commas if needed and import the start and end columns as Excel time values. All times are local to the same site time zone. For a live workbook, filter both source tabs to the day being checked, and validate that each end follows its start.
Availability
Resource,Date,Available from,Available until
TECH-01,2026-10-28,09:00,12:00
TECH-01,2026-10-28,13:00,15:00
TECH-02,2026-10-28,09:00,12:00
TECH-03,2026-10-28,09:00,12:00
Assignments
Booking,Resource,Date,Start,End,Site,Status
JOB-401,TECH-01,2026-10-28,09:00,11:00,Site North,Confirmed
JOB-402,TECH-01,2026-10-28,10:30,13:30,Site South,Confirmed
JOB-403,TECH-01,2026-10-28,14:00,15:00,Site North,Confirmed
JOB-404,TECH-02,2026-10-28,09:00,10:00,Site West,Confirmed
JOB-405,TECH-02,2026-10-28,10:00,12:00,Site West,Confirmed
JOB-406,TECH-03,2026-10-28,09:00,12:00,Site South,Tentative
JOB-407,TECH-03,2026-10-28,11:00,12:00,Site South,Confirmed
In Availability, enter =ROUND(C2*1440,0) and =ROUND(D2*1440,0) in E2:F2 and fill through row 5. In Assignments, enter =ROUND(D2*1440,0) and =ROUND(E2*1440,0) in H2:I2 and fill through row 8. These express the times in whole minutes after midnight.
In a Slots sheet, repeat each technician in column A for 12 rows. In column B, give each technician the same 12 slot starts from 09:00 to 14:30. Start at =TIME(9,0,0) and add 1/48 for each next slot, restarting at 09:00 for each technician. Put these three formulas in C2:E2 and fill through row 37. They give the slot’s start minute, count of matching availability windows and count of confirmed bookings.
=ROUND(B2*1440,0)
=COUNTIFS(Availability!$A$2:$A$5,A2,Availability!$E$2:$E$5,"<="&C2,Availability!$F$2:$F$5,">"&C2)
=COUNTIFS(Assignments!$B$2:$B$8,A2,Assignments!$H$2:$H$8,"<="&C2,Assignments!$I$2:$I$8,">"&C2,Assignments!$G$2:$G$8,"Confirmed")
In F2:K2, enter these formulas for available, raw confirmed, outside availability, duplicate within availability, distinct booked within availability and unbooked minutes. Fill through row 37 and sum each column. The 30-minute grid is exact for this example because every endpoint is aligned to it. If appointments begin at arbitrary times, split the day at every availability and booking start and end, and use each segment’s actual duration in place of 30.
=30*--(D2>0)
=30*E2
=IF(D2=0,30*E2,0)
=IF(D2>0,30*MAX(E2-1,0),0)
=30*--AND(D2>0,E2>0)
=30*--AND(D2>0,E2=0)
Find the conflict and the time you can actually use
At 10:30 a.m., TECH-01 has two confirmed bookings. JOB-401 ends at 11:00 and JOB-402 continues, making the overlap 30 minutes. JOB-402 also crosses the noon-to-1 p.m. break. TECH-01 has a free half hour at 1:30 p.m. TECH-02’s jobs meet at 10:00 exactly, so they do not overlap. TECH-03 has 120 unbooked minutes before 11:00 because the other booking is tentative.
The team has 660 available minutes and 600 raw confirmed minutes. Of the bookings, 60 minutes are outside availability and 30 are duplicate demand within it. That leaves 510 distinct booked minutes and 150 unbooked minutes. Those 150 minutes sit in specific windows and require a match on technician, duration and location before accepting another job.
Trace the conflict back to the bookings