Excel Guides

How to Calculate Effort-Weighted Project Progress in Excel

Three tasks report 100%, 50% and 25% complete. Their average is 58.3%. Weight those same tasks by their planned hours and progress falls to 32.5%. A fourth task has no update, so the whole project needs a range.

A Smartsheet user asked how to weight child tasks while leaving schedule lag out of the progress calculation. Smartsheet’s parent rollup uses child duration when dependencies are enabled. If your reporting policy uses planned labor effort instead, calculate a separate measure with the approved effort field. Keep both measures labeled in the dashboard.

Choose the work that belongs in the measure

Use the lowest-level active tasks. Parent rows summarize work that already appears below them. Waiting periods and zero-hour milestones can belong on the timeline. This example excludes them from effort, along with cancelled tasks. Keep planned hours separate from schedule duration and time actually worked.

Copy the synthetic project export

Import this fictional fit-out plan into A1:F9. Import progress as a decimal from 0 to 1 and leave T04’s progress genuinely blank. Format the progress column as a percentage if you like.

ID,Type,Scope,PlannedHours,Progress,ScheduleDays
P01,Parent,Active,50,0.75,15
T01,Task,Active,2,1,1
T02,Task,Active,6,0.5,2
T03,Task,Active,32,0.25,4
T04,Task,Active,10,,3
L01,Wait,Active,0,,5
M01,Milestone,Active,0,1,0
T05,Task,Cancelled,8,0.5,2

Check each task before weighting it

Put the next formulas in G2 and H2 and fill down through row 9. Active tasks need a unique ID and positive numeric planned hours. Blank progress is pending. A recorded zero is a known update. Earned planned hours are the agreed weight multiplied by the reported progress estimate.

=IF(OR(B2<>"Task",C2<>"Active"),"Excluded",IF(OR(A2="",COUNTIF($A$2:$A$9,A2)<>1),"Review",IF(OR(NOT(ISNUMBER(D2)),D2<=0),"Review",IF(E2="","Pending",IF(AND(ISNUMBER(E2),E2>=0,E2<=1),"Known","Review")))))
=IF(G2="Known",D2*E2,"")

Put the following formulas in K2 through K10, one per cell. They return the number of known tasks, known planned hours, earned planned hours, weighted progress for the known tasks, simple average for the same tasks, pending planned hours, all in-scope hours, and the lower and upper bounds. Format K5, K6, K9 and K10 as percentages. Update the ranges for a longer export.

=COUNTIF(G2:G9,"Known")
=SUMIF(G2:G9,"Known",D2:D9)
=SUM(H2:H9)
=IF(K3=0,"",K4/K3)
=IF(K2=0,"",AVERAGEIF(G2:G9,"Known",E2:E9))
=SUMIF(G2:G9,"Pending",D2:D9)
=IF(COUNTIF(G2:G9,"Review")>0,"Review",K3+K7)
=IF(AND(ISNUMBER(K8),K8>0),K4/K8,"Review")
=IF(AND(ISNUMBER(K8),K8>0),(K4+K7)/K8,"Review")

Report coverage alongside progress

T01 earns 2 planned hours, T02 earns 3 and T03 earns 8. Together they earn 13 of the 40 planned hours with updates. That is 32.5% with 40 of 50 planned hours covered. The simple average is 58.3% because it gives the two-hour task and the 32-hour task equal weight.

T04 accounts for ten planned hours. At 0%, the full-scope number would be 13/50, or 26%. At 100%, it would be 23/50, or 46%. Display that range while you wait for an update. When every in-scope row has known progress, the bounds converge. If an in-scope planned weight is missing or an input is invalid, fix the input before showing either bound.

Trace the dashboard figure to the task rows

In Jolene.pro, ask which workbook rows contribute to the earned-hours numerator, which rows set the denominator, and which task prevents a single project-wide figure. Check T03’s planned hours and T04’s blank update against the cited cells. Save the check to rerun on the next status export with the same reporting policy. A live Jolene.pro result was not verified for this example.