How to Check for Missing Timesheets Before Reporting Project Costs

The Monday project dashboard shows $1,130 of the weekly labor budget left. Two of ten expected timesheets are still outstanding. Show the $1,130 as provisional and put the submission count beside it. Someone who submitted zero project hours belongs in the received count.

This check follows a design and construction staffing discussion about weekly cost reporting when a spreadsheet is updated by hand and late. If your time system lists missing and submitted sheets by period, start there. Deltek Vantagepoint, for example, lists Missing, In Progress and Submitted separately. Confirm which statuses your team accepts for a provisional view. A report of posted labor needs a different status rule.

Start with the people expected to submit

Synthetic example. This is the weekly labor view for one project. On a sheet named Roster, enter ID in A1 and E01 through E10 in A2:A11. The roster includes only people expected to submit during the example week. Enter 2026-W46 in H1 and 4000 in H2 for that week’s labor budget. Keep the same project, week and snapshot cutoff on both sides.

Paste the table into A1:E11 on a sheet named Time. The ten activity rows cover two weeks. Each employee-week has one current submission record, with hours and booked or provisional labor cost for this project only. If you start from multiple task lines, roll up cost and hours by person and week and attach the authoritative timesheet status. Check numeric fields before using the formulas. A person may appear with a submitted sheet and explicit zero project hours even if the project export has no detail for them.

IDWeekStatusProject hoursProject labor USD
E012026-W46Approved8640
E022026-W46Submitted6480
E032026-W46Submitted00
E042026-W46Approved5450
E052026-W46Submitted4320
E062026-W46Approved7560
E072026-W46Submitted3240
E082026-W46Submitted2180
E092026-W46Draft5500
E102026-W45Approved3240

Count received sheets and total only their project labor

Add Rows, Valid status, Hours, Labor and Check to Roster!B1:F1. Paste the five formulas across B2:F2 and fill down to row 11. The accepted statuses for this exercise are Submitted and Approved. The ranges include one spare row for the duplicate test.

=COUNTIFS(Time!$A$2:$A$12,A2,Time!$B$2:$B$12,$H$1)
=COUNTIFS(Time!$A$2:$A$12,A2,Time!$B$2:$B$12,$H$1,Time!$C$2:$C$12,"Submitted")+COUNTIFS(Time!$A$2:$A$12,A2,Time!$B$2:$B$12,$H$1,Time!$C$2:$C$12,"Approved")
=IF(AND(B2=1,C2=1),SUMIFS(Time!$D$2:$D$12,Time!$A$2:$A$12,A2,Time!$B$2:$B$12,$H$1),"")
=IF(AND(B2=1,C2=1),SUMIFS(Time!$E$2:$E$12,Time!$A$2:$A$12,A2,Time!$B$2:$B$12,$H$1),"")
=IF(B2=0,"Missing",IF(B2>1,"Review duplicate",IF(C2=1,"Received","Not submitted")))

In H3:H7 enter the summary formulas below, one per cell. They return received count, expected count, received hours, received labor and the provisional budget remaining.

=COUNTIF(F2:F11,"Received")
=COUNTA(A2:A11)
=SUM(D2:D11)
=SUM(E2:E11)
=H2-H6

8 of 10 received, 35 project hours and $2,870 in submitted or approved labor. Provisional budget remaining: $1,130. E03 is received with zero in Time!D4:E4. E09 is a draft at Time!C10, so its $500 stays out. E10 only has a previous-week record at Time!B11. A copy of E01’s activity in row 12 should flag Review duplicate and keep E01 out of the received total until resolved. Remove the copy after testing.

Use a consistent week key and keep one row per expected person. In Power Query, check duplicate person-week keys first. Then use a left anti join from the expected roster to the valid submissions for that week to find the people still outstanding. Keep the draft and missing categories visible in the report. The example measures labor against its budget. A fee-burn or margin report can also include other costs, which need separate source records.

To check the supporting workbook in Jolene.pro, try: “Compare the Roster with Time for 2026-W46. Show the received count, missing or draft submissions, verified zero-hour submissions and the cells behind the provisional labor total. Flag duplicates before summing.” Verify the cited rows before reusing the question for another week. These synthetic figures were checked independently. A live Jolene.pro result was not verified.

Once all expected weekly records are approved, calculate average overtime per eligible employee-week to compare workload across weeks and employees with different start dates.