How to check material requests against an approved bill of quantities

Fictional project P1 has requests for 60 m and 50 m against an approved quantity of 100 m, an excess of 10 m.

Before approving another material request, add up the quantities already requested against that project line. Compare the total with the current approved bill of quantities, or BOQ.

Records to compare

Choose an as-of time and keep the approved revision in its own column. Join requests to the project and BOQ line. Write down which statuses count in your review and convert units only with an approved conversion. Compare linked orders separately so that an open order behind a cancelled request still gets reviewed.

Worked example with fictional records

RecordIncluded quantityReview state
R1 approved100 mApproved limit
M1 and M2110 mSubmitted
Difference10 mAbove limit

BOQ!A2:F3 shows 100 m approved and a draft of 120 m. Requests!A2:F5 shows two submitted P1/B1 lines of 60 m and 50 m. Subtract 100 m from 110 m to get a 10 m excess. M3 is cancelled and excluded under the fictional rule. M4 belongs to another project. Downstream!A2:C2 still shows an open PO linked to M3.

Try it in Jolene.pro

What to check before acting

If M2 is in rolls and the conversion is missing, as in UnitControl!A2:D2, leave the excess unresolved. Check the effective approval date and duplicate request lines before acting. Keep approvals in your native system. This review does not establish that ERPNext will enforce a BOQ ceiling.

Download the fictional practice files

Copy the practice data
BOQ.csv
projectlinerevisionstateqtyunit
P1B1R1approved100m
P1B1R2draft120m
Downstream.csv
requestorderstate
M3PO1open
Requests.csv
projectlineidstateqtyunit
P1B1M1submitted60m
P1B1M2submitted50m
P1B1M3cancelled20m
P2B1M4submitted10m
UnitControl.csv
requestqtyunitapproved_conversion
M250roll