How to Check Whether a Bake Plan Fits the Fridge
A bake schedule can work on paper and still need more trays in the fridge than it can hold. Put a start time, end time and slot count beside each batch, including trays already in storage.
Work through a synthetic example
| FridgePlan row | What goes in | From | Until | Slots |
|---|---|---|---|---|
| 2 | Trays already stored | 08:00 | 15:00 | 2 |
| 3 | Batch A | 09:00 | 12:00 | 4 |
| 4 | Batch B | 10:00 | 14:00 | 4 |
At 10:00 all three rows are active. The plan needs ten slots and capacity is eight. If Batch B can move to 12:00 after A leaves, the synthetic peak falls to six.
Check your own records
- Put date and start time in C, date and end time in D, and slots in E. Put the time to inspect in H2. Use
=SUMIFS($E$2:$E$4,$C$2:$C$4,"<="&H2,$D$2:$D$4,">"&H2)for the table above. - Check every entry and exit time, including trays carried over from the previous day. Flag missing or reversed time ranges and loads that exceed usable capacity.
- If two batches meet at one timestamp, decide who leaves first or add a buffer. Check the production deadline and storage requirements before altering the plan.
This checks scheduling capacity using your recorded tray times. It makes no claim about safe storage conditions for a recipe.