How to Find Packaging Quotes That Understate Short-Run Costs
The short runs shipped on time. They still took almost as long to set up as jobs four times the size. Compare what the estimator allowed with what production recorded.
What to pull
Use Excel estimate and job-cost tabs, or export quoted routing from estimating and actual time and material from shop-floor software. Keep job, run size, setup minutes and machine.
How to check it
Match by job and operation. Separate setup time, run time and material scrap. Compare repeat work on the same equipment and group by run size.
Which quote assumptions understate repeat short-run costs? Show the biggest recurring differences and source rows.
What to do with the result
If setup regularly takes 55 minutes against 30 quoted, review that setup allowance for the next comparable quote with estimating.
Use approved labor rates and review one-off trial jobs separately.